The First Draw

So we’re at the point where we need to make the first draw. A draw is what happens when the 203k contractor has completed enough of the work, at cost to him, to get reimbursed from the bank/loan. The contractor submits an expense sheet, the 203k consultant inspects the work and signs off, and then the bank cuts a check.

20160405_195655
New doorway into the kitchen.
20160405_195708
The reading nook transformed into a laundry/pantry.
20160405_195746
The old kitchen doorway being closed off.
20160405_195920
New plumbing, hurray.
20160405_200612
The rotted boards of the porch have been replaced.
20160405_200620
This area was particularly problematic with rot, particularly since it holds up the rest of the porch.